Construction Activities - Canada

Canadian Port of Entry (POE)

  • Crews complete slab on grade preparations and continue block wall, interior plumbing, electrical and HVAC rough-in work for the maintenance building.
  • Structural steel activities, underground plumbing, backfilling activities as well as second-floor and third-floor hangar installation work continues for the main building.
  • Structural steel erection is being completed and slab on grade preparation work begins for the secondary inspection building.
  • Slab on grade preparations and underground service work is taking place on the client processing building.
  • Reinforcing steel, formwork for pier foundations and booths as well as placement of concrete for footings and booth walls continue for primary inspection lanes.
  • Footing and wall formwork and reinforcing steel and concrete placement for the footings and foundations continue for the tolling building.
  • Toll plaza pier and booth foundation excavation is being completed and work begins on reinforcing steel for the piers. 

Canadian Bridge site

  • Modifications continue to the tower jump forms.
  • Concrete, rebar and formwork continue in the transition area from tower legs to pylon head.
  • Concrete, rebar and formwork continue for side span pier work.
  • Approach bridge pile driving continues this week. • Preparations continue for pier table steel erection work. 

 