Construction Activities - Canada

Canadian Port of Entry (POE)

  • Interior plumbing, electrical and HVAC rough-ins continue for the maintenance building, as team begins painting preparations.
  • Underground utility work, slab on grade preparations, reinforcing steel and formwork as well as slab on deck
    activities continue for the main building.
  • Temporary roof is being completed as slab on grade preparations continue for the secondary inspection
    building.
  • Excavation work for the pier foundation, reinforcing steel, concrete and formwork continue for the secondary
    inspection canopy.
  • Temporary roof and reinforcing steel for slab on grade work is being completed for the client processing
    building.
  • Structural steel erection continues for the primary inspection lane canopy.
  • Waterproofing and backfilling activities continue for the tolling building.
  • Formwork, reinforcing steel and sleeving continues for the booths at the tolling plaza.
  • Surcharge activities continue in the inbound traffic area and at the east gateway.
  • Underground utility work is ongoing.

Canadian Bridge site

  • Rebar activities continue for the upper cross beam in the transition area for the tower.
  • Installation of soffit panels continue.
  • Concrete, rebar and formwork continue for back span piers.
  • Pile driving continues for the approach bridge.
  • CanAm steel for the bridge deck and anchor boxes continue to arrive on site.