Construction Activities - Canada
Canadian Port of Entry (POE)
- Interior plumbing, electrical and HVAC rough-ins continue for the maintenance building as well as the priming of the interior precast panels, framing of interior partitions and prep work for the roofing installation.
- Underground utility and slab on grade preparations continue for the Main building, while multiple concrete slab
on deck placements are completed. - Slab on grade preparations continue for the secondary inspection building.
- Reinforcing steel and formwork for the pier foundations continue for the secondary inspection canopy.
- Slab on grade placement and interior partition layout work is being completed for the client processing building.
- Structural steel erection continues for the primary inspection lane canopy.
- Structural steel work continues for the tolling building.
- Concrete placements for piers and booths are being completed for the tolling plaza.
- Crews are completing subgrade cut and beginning subdrains in inbound traffic area.
- Underground utility work is ongoing.
Canadian Bridge site
- Rebar activities continue for the upper cross beam in the transition area of the tower legs.
- Floor beams, edge and redundancy girders are being erected at the pier table.
- Concrete, rebar and formwork continue for back span piers.
- Pile driving continues for the approach bridge.
- Approach bridge foundation, rebar and formwork now underway.
- CanAm steel for the bridge deck and anchor boxes continue to arrive on site.