Construction Activities - Canada

Canadian Port of Entry (POE)

  • Interior plumbing, electrical and HVAC rough-ins continue for the maintenance building as well as the priming of the interior precast panels, framing of interior partitions and prep work for the roofing installation.
  • Underground utility and slab on grade preparations continue for the main building, while multiple concrete slab on deck placements are completed.
  • Slab on grade preparations continue for the secondary inspection building.
  • Reinforcing steel and formwork for the pier foundations continue for the secondary inspection canopy.
  • Mechanical and electrical rough-in work is now underway for the client processing building as work continues
    on the interior partition layout.
  • Structural steel erection continues for the primary inspection lane canopy.
  • Structural steel work continues for the tolling building.
  • Backfill activities continue for the tolling plaza as teams continue hauling off excess material.
  • Subdrain work continues in the inbound traffic area.
  • Underground utility work is ongoing.

Canadian Bridge site

  • Rebar activities continue for the upper cross beam in the transition area of the tower legs.
  • Floor beams, edge and redundancy girders are being erected at the pier table.
  • Concrete, rebar and formwork continue for back span piers with the installation of the soffit cross beam.
  • Pile driving continues for the approach bridge.
  • Approach bridge foundation, rebar and formwork continue this week.
  • CanAm steel for the bridge deck and anchor boxes continue to arrive on site.