Construction Activities - Canada

Canadian Port of Entry (POE)

  • Interior plumbing, electrical, HVAC and fire suppression rough-ins continue for the maintenance building as well as painting, framing of interior partitions and prep work for the roofing installation.
  • Underground utility and slab on grade placements continue for the main building as work begins on the roof and framing and block walls on the second and third floors.
  • Installation of interior plumbing, electrical, HVAC and fire suppression rough-ins continue for the secondary
    inspection building as work begins on the block walls.
  • Reinforcing steel and formwork for the pier foundations continue for the secondary inspection canopy.
  • Framing and block wall work is now underway as the installation of interior plumbing, electrical, HVAC and fire
    suppression rough-ins continue for the client processing building.
  • Structural steel erection continues for the primary inspection lane canopy.
  • Structural steel work is being completed as underground utility work begins for the tolling building.
  • Backfill activities are being completed for the tolling plaza.
  • Subdrain work continues in the inbound traffic area.
  • Work is underway on the retaining wall and concrete paving at the east gateway.
  • Underground utility work is ongoing.

Canadian Bridge site

  • Rebar activities continue for the upper cross beam in the transition area of the tower legs.
  • The approach and back span activities are ongoing with cross beam rebar installation taking place in the back span and formwork in the approach span.
  • Delivery of soffits and edge girders are ongoing.
  • 79 precast panels for the deck have been delivered to date.
  • Two of the temporary lock up devices arrived on site this week and the team will begin installation next week.