Construction Activities - Canada
Canadian Port of Entry (POE)
- Main Building: Continued framing and block wall work as well as the installation of interior plumbing, electrical, HVAC, Controls and fire suppression.
- Primary Inspection Lanes (PIL) Pavilion: Completed foundation walls of building. Continued work on north bridge foundation and on underground utilities. Continued installation of crash blocks.
- Maintenance Building: Continued installation of interior plumbing, electrical, HVAC and Controls. Continued roofing work and preparation for rolling door installation.
- Tolling Building and Canopy: Continued installation of curtain walls. Completed structural steel erection and detailing.
- Hazmat Canopy: Completed structural steel erection and decking. Began underground work and Slab on Grade.
Canadian Bridge site
- Rebar stitch pours are ongoing and rebar work continues.
- Installation on the deck continues.
- Approach and back span activities are ongoing.
- Stay cable installation work continues.
- Steel for bridge deck and anchor boxes continue arriving on-site. Precast panels continue arriving on-site.