Construction Activities - Canada

Canadian Port of Entry (POE)

  • Main Building: Continued framing and block wall work as well as the installation of interior plumbing, electrical, HVAC, Controls and fire suppression.
  • Primary Inspection Lanes (PIL) Pavilion: Completed foundation walls of building. Continued work on north bridge foundation and on underground utilities. Continued installation of crash blocks.
  • Maintenance Building: Continued installation of interior plumbing, electrical, HVAC and Controls. Continued roofing work and preparation for rolling door installation.
  • Tolling Building and Canopy: Continued installation of curtain walls. Completed structural steel erection and detailing.
  • Hazmat Canopy: Completed structural steel erection and decking. Began underground work and Slab on Grade.

Canadian Bridge site

  • Rebar stitch pours are ongoing and rebar work continues.
  • Installation on the deck continues.
  • Approach and back span activities are ongoing.
  • Stay cable installation work continues.
  • Steel for bridge deck and anchor boxes continue arriving on-site. Precast panels continue arriving on-site.