Construction Activities - Canada

Canadian Port of Entry (POE)

  • Main Building: Continued framing, mesh installations and drywall on the first, second and third floors. Started installation of interior plumbing, electrical and HVAC.
  • Maintenance Building: Continued installation of interior plumbing, electrical, HVAC and Controls.
  • Tolling Building and Canopy: Completed installation of curtain wall panels. Began installation of soffit sub-framing.
  • Hazmat Canopy: Completed structural steel erection and decking. Began underground work and Slab on Grade.

Canadian Bridge site

  • Rebar stitch pours are ongoing and rebar work continues.
  • Installation on the deck continues.
  • Approach and back span activities are ongoing.
  • Stay cable installation work continues.