Construction Activities - Canada
Canadian Port of Entry (POE)
- Main Building: Continued framing, mesh installations and drywall on the first, second and third floors. Started installation of interior plumbing, electrical and HVAC.
- Maintenance Building: Continued installation of interior plumbing, electrical, HVAC and Controls.
- Tolling Building and Canopy: Completed installation of curtain wall panels. Began installation of soffit sub-framing.
- Hazmat Canopy: Completed structural steel erection and decking. Began underground work and Slab on Grade.
Canadian Bridge site
- Rebar stitch pours are ongoing and rebar work continues.
- Installation on the deck continues.
- Approach and back span activities are ongoing.
- Stay cable installation work continues.