Construction Activities - Canada

Canadian Port of Entry (POE)

  • Energy Building: Continued cable pulls for control systems.
  • Main Building: Continued framing, mesh installations and drywall on the first, second and third floors. Continued block wall installation and commenced full roof.
  • Maintenance Building: Completed full roof. Continued installation of interior plumbing, electrical, HVAC and Controls.
  • Return to USA Bridge: Received mechanically stabilized earth (MSE) wall and commenced installation.
  • Utilities: Began backfill of hydronics trench.

Canadian Bridge site

  • Rebar stitch pours are ongoing and rebar work continues.
  • Installation on the deck continues.
  • Approach and back span activities are ongoing.
  • Stay cable installation work continues.
     