Construction Activities - Canada
Canadian Port of Entry (POE)
- Secondary Inspection Building: Completed parapet framing.
- Client Processing Building: Completed precast wall installation.
- Large Scale Imaging Building: Continued work on concrete walls. Continued electrical, mechanical and plumbing rough ins.
- Tolling Building: Continued stud framing inside the building. Started parapet framing.
- Tolling Canopy: Continued soffit sub framing and Lane Control Signs framing.
- Hazmat Canopy: Completed catch basin pours and began catch basin tie ins.
- Utilities: Completed backfill of hydronics trench.
Canadian Bridge site
- Rebar stitch pours are ongoing and rebar work continues.
- Installation on the deck continues.
- Approach and back span activities are ongoing.
- Stay cable installation work continues.