Member for

2 years 10 months

Construction Activities - Canada

Canadian Port of Entry (POE)

  • Secondary Inspection Building: Completed parapet framing.
  • Client Processing Building: Completed precast wall installation.
  • Large Scale Imaging Building: Continued work on concrete walls. Continued electrical, mechanical and plumbing rough ins.
  • Tolling Building: Continued stud framing inside the building. Started parapet framing.
  • Tolling Canopy: Continued soffit sub framing and Lane Control Signs framing.
  • Hazmat Canopy: Completed catch basin pours and began catch basin tie ins.
  • Utilities: Completed backfill of hydronics trench.

Canadian Bridge site

  • Rebar stitch pours are ongoing and rebar work continues.
  • Installation on the deck continues.
  • Approach and back span activities are ongoing.
  • Stay cable installation work continues.
On
Canada
Off