Construction Activities - Canada
Canadian Port of Entry (POE)
- Maintenance Buildings: Continued installation of interior plumbing, electrical, HVAC and Controls. Continued preparation for rolling door installation. Commenced drywall installation.
- Secondary Inspection Building: Commenced full roof.
- Client Processing Building: Completed precast wall installation. Commenced curtain wall installation.
- Large Scale Imaging Building: Continued concrete walls for electrical and mechanical rooms. Continued electrical, mechanical and plumbing.
- Hazmat Canopy: Commenced perimeter framing. Completed storm pipe installation.
Canadian Bridge site
- Rebar stitch pours are ongoing and rebar work continues.
- Installation on the deck continues.
- Approach and back span activities are ongoing.
- Stay cable installation work continues.