Construction Activities - Canada
Canadian Port of Entry (POE)
- Main Building: Continued framing, mesh installs and drywall on first, second and third floors. Continued block wall installation in south end. Continued forming and rebar installation in south tower. Completed full roof on Canadian Food Inspection Agency space.
- Primary Inspection Lane Canopy: Continued gutter framing and soffit sub-framing. Commenced Lane Control Sign framing installation.
- Primary Inspection Lane Pavilion: Continued installation of crash blocks in lanes. Foundation walls and piers were completed and cured. Area scrubbed in preparation for structural steel arrival.
- Large Scale Imaging Building: Continued concrete walls for electrical and mechanical rooms.
- Tolling Building: Continued stud framing inside the building. Continued parapet framing.
Canadian Bridge site
- Rebar stitch pours are ongoing and rebar work continues.
- Installation on the deck continues.
- Approach and back span activities are ongoing.
- Stay cable installation work continues.