Construction Activities - Canada

Canadian Port of Entry (POE)

  • Main Building: Completed dock leveler installation.
  • Client Processing Building: Began parapet installation.
  • Large Scale Imaging Building: Continued concrete walls for electrical and mechanical rooms. Began slab on grade.
  • Tolling Building: Began full roof installation.
  • Dry Utilities: Completed excavation of High Mast light pole foundations. Completed excavation of gantry foundations.

Canadian Bridge site

  • Rebar stitch pours are ongoing and rebar work continues.
  • Installation on the deck continues.
  • Approach and back span activities are ongoing.
  • Stay cable installation work continues.