Construction Activities - Canada
Canadian Port of Entry (POE)
- Construction activities remain ongoing for interior and exterior components of the buildings and structures. •
- This week, activities include utility work, roof installation, parapet installation, preparation for curtain walls and concrete placement.
- Work continues for the 401 approach
Canadian Bridge site
- Cap construction continued at anchor pier.
- Rebar installation ongoing for tower upper pylon construction.
- Installation of main span segment panels continued.
- Stay cable installation work continues.
- Approach and back span activities are ongoing.
- Side span structural steel installation finished.