Construction Activities - Canada

Road Closure

Sandwich Street

  • Partial Closure of Sandwich Street between the Essex Terminal Railway easement (ETR) tracks and Chappell Avenue anticipated to start September 5, 2023 for 14 weeks.
  • For more information about active road closures, we encourage you to visit the project website at GordieHoweInternationalBridge.com.

Canadian Port of Entry (POE)

  • Construction activities remain ongoing for interior and exterior components of the buildings and structures.
  • This week, activities include concrete pouring for slabs in various locations and installation of electrical handholes in steel columns. Fencing installation continues, as well.

Canadian Bridge site

  • Cap construction continued at anchor pier.
  • Rebar installation ongoing for tower upper pylon construction.
  • Installation of main span segment panels continued.
  • Stay cable installation work continues.
  • Approach and back span activities are ongoing.