Construction Activities - Canada

Canadian Port of Entry (POE)

  • Construction activities remain ongoing for interior and exterior components of the buildings and structures.
  • This week, crews poured approach slabs for various buildings while the installation of light fixtures and electrical rough-ins continued.
  • Installation of millwork, parapet walls, ceiling grids and canopy roofing also continue.
  • Preparations are ongoing for the arrival of generators.
  • Ponds are now active and draining to the Broadway Drain.

Canadian Bridge site

  • Cap construction continued at anchor pier.
  • The Canadian bridge tower has reached its full height of 220 metres/722 feet. The jump form system has been completely removed
  • Installation of main span segment panels continued.
  • Stay cable installation work continues.
  • Approach and back span activities are ongoing.
  • Approach bearings and girders installation complete. Crews continue to torque and weld bearings.
On
Canada
Off