Construction Activities - Canada
Canadian Port of Entry (POE)
- Construction activities remain ongoing for interior and exterior components of the buildings and structures.
- This week, crews poured approach slabs for various buildings while the installation of light fixtures and electrical rough-ins continued.
- Installation of millwork, parapet walls, ceiling grids and canopy roofing also continue.
- Preparations are ongoing for the arrival of generators.
- Ponds are now active and draining to the Broadway Drain.
Canadian Bridge site
- Cap construction continued at anchor pier.
- The Canadian bridge tower has reached its full height of 220 metres/722 feet. The jump form system has been completely removed
- Installation of main span segment panels continued.
- Stay cable installation work continues.
- Approach and back span activities are ongoing.
- Approach bearings and girders installation complete. Crews continue to torque and weld bearings.